Workload by assignee - Summary Report after Sprint is closed?

athomas3 September 24, 2018

Team:

I don't see this as a report that I may access after the sprint has completed. If it's valuable during the sprint, it's valuable after the sprint.

 

Am I missing this reporting somewhere or should I have to do this manually?

1 answer

0 votes
Burak Kocak
Contributor
September 24, 2018

Worklogs not stored by sprint but by issue. I assume that you are using jira with out plugins under this assumption 

use jql :

project =<your project> And sprint = <your sprint> to get your issues in specific sprint. 

Than add timespent columns to learn total amount of worklogs 

But this make a false report if your issue enter more than one sprint. 

athomas3 September 24, 2018

I can look at the Sprint Report for specific project and sprint metrics as they pertain to issues, but not by assignee.

When you click on the ... you get a report that basically states assignee, the number of issues assigned, and total story points assigned per team member. This equates to the velocity planned per assignee, per sprint which is very beneficial for Sprint Planning.

My issue is as we plan issues for team members, and we have an active sprint,

1. I can't see what was pulled into the sprint from the backlog.

2. When the sprint is completed, there is no report based on the attributes of this Workload by Assignee feature that I can access after the sprint is closed for Sprint Review tracking.

3. I cant download any of this information for reporting purposes or tracking purposes.