Hi All,
I want the Efforts mentioned/registered in ‘Sub Tasks’ to get consolidated or added up to their respective “User Story” / "Task"
Is this possible in JIRA Software ? If yes, how should I do it...,
Pls advise…,
Thanks in Advance !!!
Warm Regards,
Vignesh
Yes, time logged against sub-tasks can be shown on the parent story, using the "include sub-tasks" option in the Time Tracking section on the Story.
However, if you are using the "new issue view", there is a known bug where this doesn't display:
https://jira.atlassian.com/browse/JRACLOUD-69587
But you can switch the new view off:
https://confluence.atlassian.com/jiracorecloud/the-new-jira-issue-view-938040503.html
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.