Hi, 

On Jira cloud, I use Plans to create my roadmap.

About capacity planning, it is possible to change  the capacity sprint for all sprint. yet, i have 200h per sprint, i want to reduce it.

If i want capacyty per person, i'm need to crate a team of 1 person ? or do you have any suggestions ?

Best regards, 

Melanie

 

 

1 answer

1 accepted

1 vote
Answer accepted
Jacob Vu
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 31, 2021

Hi @Mélanie Liguet

If you're looking to adjust capacity sprints for teams, you'd have to click the Teams tab and click the edit button under each team's arrows.

If you want capacity per person, the only way I can think of it right now is to create it per person like you mentioned.

Hope this helps.