keshav_goyal0212 February 27, 2021

I have 4 task project to complete in two month, Each task has 2 week time to complete , but one task gets delayed by 2 weeks . But i want the remaining task complete within month soo how in roadmap their time duration automatically get cut and Adjusted? 

 

1 answer

1 accepted

4 votes
Answer accepted
Michael Moschitta
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 28, 2021

Are the tasks sequential?  or independent?   3 tasks have 2 weeks each to complete so would complete within a month. the 4th one gets delayed by 2 weeks and therefore takes a month

keshav_goyal0212 February 28, 2021

Tasks are ssequentially , Basically want to know how can make automation in my road map , Like if 1 task gets delayed, Then the remaining 3 are adjusted within the given time. And in the roadmap delayed effect been shown as the time for each task get a cut so that they can be done with the given time.

Michael Moschitta
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 28, 2021

ok.. so for example if A gets delayed 2 weeks, then B and C dates can pushed for 2 weeks as well?  i have some time tomorrow to look at this.. 

Michael Moschitta
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 28, 2021

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
TAGS
AUG Leaders

Atlassian Community Events