can an agile sprint include tasks from multiple projects?

silverrailtech September 22, 2014

Hey there,

Our team has tasks driven from two different sources that are managed by two different projects.

We need to estimate and log work against known tasks at the start of a sprint, as well as for additional tasks during a sprint.   

But I want to plan and manage the sprint in one Agile board that includes tasks from both projects.

Is this possible?  If so, how?

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 22, 2014

Yes.  That's the simple answer.

All you need to do is change the filter for the Agile board so that it includes both projects.  Then you'll see all the issues together and can drag them into the sprint as required.

silverrailtech September 22, 2014

Oh perfect! Thanks mate.