change colour of individual epics based off status on Timeline

Anita Pallas December 10, 2023

Hello

Is there a way to change an items colour on a Planners Timeline depending on the status?

1 answer

0 votes
Murat Seven
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 11, 2023

Hi @Anita Pallas  and Welcome to the Atlassian Community!

 

On the timeline, you can change the color of parent issue’s schedule bar, which is then applied to all of its child issues.

 

to change the color of schedule bars from the issue side view:

  1. Select the issue schedule bar to open the side view.
  2. Next, select the colored square next to the issue summary to open the picker.
  3. Choose your color, and your change is automatically applied.

 

To change the color directly from the schedule bar:

  1. Right click on the schedule bar (or hold control before clicking).

  2. Choose a color from the menu.

following docs.

 

But, 

If you are working with a Work Management project, you cannot arbitrarily set the color of those bars, nor have it based on issue type.

According to the documentation here the bar colors are based on the Status of the related issue. If the Status is part of the "To Do" Status Category, the color will be dark blue.

 

If the issue is resolved, you can vote for this comment.

Hope this helps.

Best,

Murat Seven 

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events