All calculations on the backlog page are based on the original estimate. How can I change this to be based on remaining time? Also, velocity is showing based on the original estimate—how can I change it to be based on remaining time?
you can configure estimation to show remaining time instead of original estimate.
Jira will calculate sprint capacity and progress using Remaining Time instead
Hope this helps
Hello!
Unfortunately, there is no such option as "Remaining Time Estimate". The only options we see are
- Story points
- Original time estimate
- Issue count
This means we have no actual way to effectively estimate and plan a sprint due to items carried over from one sprint to another reporting its entire original estimate.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.