When i create multiple sub tasks(with estimations ) for a user story , how to configure Jira to ensure these hours added up to parent user story?
For example i have 3 tasks with estimation of 5 hours each, totaling to 15 hours, i am expecting this 15 hours to reflect at user story level. please help me
Regards,
Arvind
InJira Server: Just have to add the timetracking field in the subtask screen. The parent issue have field ∑Original Estimate that summarize estimations from the subtasks.
You need jira administration permission or extended permissions as Project Admin. TimeTracking must be enabled in the instance.
hello, I have tried to follow the steps above but still hours entered for sub task are not getting reflected in my view, i have time tracking enabled for my project, can you please give me step by step way to do this activity.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
First, are you JIRA Admin? (To see if you can check the Story screen: https://confluence.atlassian.com/adminjiraserver/defining-a-screen-938847288.html)
Send me your JIRA Version.
Could you send me print screen of what you see on the story screen (similar to the one I send).
Let’s Check in the Issues navigator to add the summarize original estimation field that I mention
1.- Go to Issues menu
2.- Search issues
3.- Add Column (image attached) -
4.- Select the field.
5.- Move the column (it will be added at the end)
And do a search of the issue, and send me the print screen. So I know what can be going on.