how to link task and make them finish-to-start

Chris January 5, 2024

Is it possible for task to have logic like finish-to-start so that when i adjust one due date the due date of the other task adjust?

1 answer

1 vote
Dag Atle Stenstad
Community Champion
January 6, 2024

Hello! Yes, it is possible to achieve this. You can use Jira Automate and set up a trigger for when the "Due date" changes. If it changes, you can then update the "Due date" on all the related issues. How you link issues together is up to you; for example, you can use linked issues or ensure that the issues are part of the same Epic.