I´wondering if there is a possibility for this:
I enter several subtasks to a parent
now i´d like to copy the assignee one after the other:
subtask 1 not done -> copy assignee 1 to parent
subtask 2 not done AND subtask 1 done -> copy assignee 2 to parent
subtask n ...
is that possible?
i´ve searched, but maybe wrong...
thank you very much for your thoughts!
bg
Andy
Andy,
Do you mean to ask if you can have multiple assignees on the parent? If this is what you mean, no it is not supported by Jira.
You could create a custom field of the type "user picker", add it to the parent issue screen, then use automation for jira to copy subtask assignees into that field.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.