Vivek Challa December 18, 2023

when we close sprint we have all reports related to sprint but it is considered only in story level for my case I want to do this metric for subtask level instead of story and task.
I want a solution to identify sprint performance at the subtask level.
I need your findings for this problem.

2 answers

2 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 19, 2023

The whole point of subtasks is that they are NOT part of a sprint.

Looking to measure sprint performance at a sub-task level is

  • smacking of the anti-pattern of micro management
  • not Agile
  • not what sub-tasks are for
  • not Scrum

I strongly recommend that you review your processes, you have a hugely broken one if you think you want to do this.

0 votes
Answer accepted
Rebekka Heilmann (viadee)
Community Champion
December 18, 2023

Have a look at this discussion: How to include sub-task in Jira sprint report? (atlassian.com)

You would most likely need 3rd party apps.

There is a number of reasons why I don't like to work with sub-tasks. I'd rather cut my stories into smaller chunks but leave them as a "normal"-level issue type. Reports is one of them

Suggest an answer