jira - projects show all issues in epic

Gavin
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 19, 2022

Hi All,

- I have a plan with an epic which task and sub tasks

- I have created a program which includes this plan.

 

When I go to the program interface

- it only shows me the that there are only 7 of the 10 tasks. 

- the 3 completed tasks does not show as a percentage complete.

 

Not sure what the issue might be

2 answers

1 accepted

0 votes
Answer accepted
Gavin
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 22, 2022

Thanks for response.  Unfortunately, something had changed in the bulk import option.  

 

The solution was:  In the bulk importer in the line item the epic link field can only have the EPIC issue id for the tasks but not for the sub task

1 vote
Josh Costella
Community Champion
January 20, 2022

Hi @Gavin

You'll want to go into your plan configuration and check how many days is set to exclude completed tickets from the view. If you're tickets were completed outside of this threshold, they will not show on the plan. 

exclusion.jpg