This question is in reference to Atlassian Documentation: Removing an Issue from a Sprint
Hi, currently when i right click an issue and then press "remove from sprint" this issue is moved to another sprint (let's call it sprint X). i want to change it so that when i choose "remove from sprint" the issue will be moved back to backlog.
where can i change this settings?
Hi,
Removing an issue from a sprint moves it to the next planned sprint, and I don't think you can alter this behaviour. If you want to move the issue to the backlog you can :
Regards,
Peter
just go the bottom at the right side and where the sprint is select (which is editable ). Click it press the back button clear the box, click the outside the box and save it. hence the goal reached issue is in the backlog. Refresh the page
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.