Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

velocity report- why commitment is different than the original estimations in the the sprint report?

Keren Hacohen Zada October 2, 2022

on the sprint report: I accumulate the left number that represent the original estimations at sprint start from all 3 categories: Completed Issues, Issues not Completed, Issues Removed From Sprint. 

it does not match the Commitment in the velocity report

2 answers

0 votes
Dan -minware-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 11, 2022

Disclaimer: marketplace partner!

Hey @Keren Hacohen Zada 

I see that you figured out the answer to you question but if you are interested in analyzing work that was added after the start of a sprint and open to marketplace partners I would like to invite you to check out minware.

You can see the burn up chart below that clearly shows the impact tickets added or removed from the start had on work-in-progress and you would simply expand the "Completed - Added After Start" to dig in:

all_tickets_flow.png

We try to make things as simple as possible so anyone on your team can understand how ticket flow impacts WIP.

Good luck finding what you are looking for, I hope this helps!

Keren Hacohen Zada October 18, 2022

thank you

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 2, 2022

Welcome to the Atlassian Community!

Have you done something like adding sprint estimates to non-sprint items (like sub-tasks)?

Keren Hacohen Zada October 6, 2022

i figured it out, In Velocity report, the committed is exactly what we had at Sprint start. if we added estimates or scope and did not complete it, it will not be counted at all. 
the completed is exactly what we have at sprint end- meaning, regardless if it was there at sprint start or added later, if it's completed- it's counted

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events