I have been using Portfolio for a while and it's the first time I get this error. I have my teams setup and I have all the necessary skills to complete the story. I can build the plan but when I assign the team the row is pink and it won't allow me to assign the team.
I searched and couldn't find any information about this error.
Not sure if this is an issue in Portfolio 2.0, but I have the fix for the legacy version
Drove me crazy all day and just figured it out.
Under: Plan > Configure > Planning > Scheduling
Scroll all the way down to: "Maximum resources"
Increase the number of resources to the maximum you want to have collaborating on them at the same time.
Good luck!
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.