Hi!
I would like to ask regarding some issues we encountered.
The "Original Estimate" field is in the ticket itself, but i cannot add it to Jira Plan, when I add the "Original Estimate" field in Jira Plan, the original estimate details in the ticket is not reflecting in Jira Plan.
The Jira Plan has Estimates but it is measured by Days.. we need to measure it by hour.
Welcome to the community.
Change the Estimation in your plan settings from days to hours.
It worked. Thank you.
One more thing. I have 2 Jira Plans for different projects. the "Estimates" field is not showing in Jira Plan.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Is the field used in the project that relates to the plan where it's no showing?
Check the fields drop-down in the pan, is the field selected?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.