My Jira is auto-updating the remaining Estimate field. In the screenshot above, I performed action 1 of updating 1d to 4d but action 2 of updating 4d to 1d was auto performed by JIRA. In history, however, it's showing that I performed that action, which is untrue.
JIRA is overwriting the remaining estimate and defaulting it to 1d or sometimes to 0
Hello @Vishwajeet Chhikara ,
Thanks for reaching out and the behavior you are seeing looks like there is possibly an automation rule or workflow post function clearing the remaining estimate.
If the action is simply editing the Original estimate that triggers the action go to the project settings > Automation and look if there is an automation rule causing the change.
Alternatively, if the Original time estimate is being changed on a transition, then check the post-functions of that transition for a 'clear field' action.
Let me know what you find.
Regards,
Earl
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.