Hi,
I am looking for a way to remove the flag automatically when the linked issue (e.g. blocked by) has been given the DONE status.
The use case is: I block a task with a linked bug and flag the original task manually. When the bug has been resolved, I want to unflag the task automatically.
I cannot find such an option in the automation screens, but maybe I'm overlooking it..?
Hi Erwin,
You can follow the below steps to do that.
1. Add a workflow step to clear the flag in the task.
2. Add a Transition Related Issues Post-function in the Done State of Bug and call the step created in #1.
Hope this solves your problem. Please accept the answer if it solves your problem.
Thanks,
Aditya