Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Report on Completed Epics

Riley Piper May 18, 2023

We are looking to create a filter to report on when an epic was completed (moved to the "done" status). We are having trouble finding a field and looking to see if the community has found a good way to report on completion dates of epics.

 

Thanks!

1 answer

1 accepted

1 vote
Answer accepted
Trudy Claspill
Community Champion
May 18, 2023

Hello @Riley Piper 

When an Epic is moved to a "done" status the Resolution field for the Epic should also be getting set. When the Resolution field is set, that causes the Resolved date/timestamp field to be set. You can use the Resolved field in filters to select issues by when they were resolved, and you can display the field in the filter results.

Riley Piper May 18, 2023

Thank you, Trudy!

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
TAGS
AUG Leaders

Atlassian Community Events