Hi All,
I have a requirement to display the progress of an Epic either in terms of percentage of story points completed or time spent over time estimated. Is there an easy way to do this? I would have thought this is a must have built in functionality. Any tips are much appreciated.
Regards,
Eshan
Hi Eshan,
I have seen a couple feature requests that resemble what you're trying to do:
The second has since been closed as a duplicate of JSWSERVER-12717. Please review JSWSERVER-12717 and vote on the issue to add impact for our developers to add this feature to JIRA in the future.
Alternatively you can also try the add-on Portfolio for JIRA which has the functionality to track progress and status:
Story point progress is calculated from the estimates set in Jira application issues. Portfolio considers an issue "Completed" when it is assigned to any status of the "Done" category, e.g, green category. The progress of an epic is computed as:
If your issues have no estimation. Progress is calculated based on the issue’s resolution field and the progress of child-issues.
Hopefully that helps!
Cheers,
Branden
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.