Reporting time a card spends from one column to another.

Pheona Bholla
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 30, 2019

Hi,

I'm wondering how I can track the amount of time a card spends transitioning from one column to another in a kanban board.

Thanks!

1 answer

0 votes
Taranjeet Singh
Community Champion
January 30, 2019

@Pheona Bholla You can use "Days in column" option in your Kanban or Scrum Board Configuration to get this information. Please see this document for more details : https://confluence.atlassian.com/jirasoftwareserver/configuring-columns-938845277.html