Separate the display of US (from cluster) in Control Chart

Arleen Grace Magday
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 19, 2021

In control chart, sometimes US are clustered (group together). Is there a way to separate the display so I can see the breakdown of the cycle time for each US? 

1 answer

0 votes
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 19, 2021

Hi @Arleen Grace Magday  -- Welcome to the Atlassian Community!

As you note, those large dots are the clusters of multiple issues with close-enough values to plot together.  There is no built-in way to see the details when they are shown clustered, however...

If you change your filters/settings, this could reduce the number of issues shown, alter the y-axis, and thus you may be able to see the separation in the values.

Two ways to do that would be to alter the time frame (select-drag over the issues) or to identify and remove any outliers with a filter.  Please look here for more information on how to use those techniques:

https://support.atlassian.com/jira-software-cloud/docs/view-and-understand-the-control-chart/

Best regards,

Bill