Maja Aagaard May 31, 2018

I am trying to get our estimates shown in the backlog.

I have followed this https://confluence.atlassian.com/jirasoftwarecloud/configuring-estimation-and-tracking-764478030.html but I still can't get it to work. 

I have created a test task, and get the "Time estimate" field here, but it is not available when creating a new task - only the estimate field (which is not shown i backlog)

How do I get "time estimate" to be a part of the create task and edit task view?

 

1.PNG2.PNG3.PNG

2 answers

0 votes
Ravi Varma
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 31, 2018

Hi @Maja Aagaard,

You should have by now enabled your board configurations to use appropriate option in Estimate tab

Please note that the create issue screen has Original Estimate field only. 

If you need further inputs on this then please provide

  • the screenshots of the board's estimate configurations
  • the view issue screenshot
  • the backlog screenshot where the current issue is selected

Regards,

Ravi Varma

0 votes
Deleted user May 31, 2018

Hi @Maja Aagaard,

Have you added the Time Tracking field to the Create and Edit screens of your Task Screen Scheme?

Thanks

Maja Aagaard May 31, 2018

Thanks for the guidance, it was missing in some of the screens

Deleted user May 31, 2018

Glad I could help :)

@Ravi Varma is also correct, I would verify your Estimation configuration located within the Board Settings.