Some stories start date appears wrong on roadmap

Eldad Dayagi
Contributor
March 10, 2023

We enabled roadmaps for one of our projects and what we are seeing is that for some of the stories under the same Epic, the start date of the story, instead of syncing with the sprint to which it is assigned, as it should, start date is somewhere in 2010 or 2013.

 

Any idea why?

The story was created recently, just as others were.

1 answer

0 votes
Walter Buggenhout
Community Champion
March 11, 2023

Hi @Eldad Dayagi,

Check the dates filled out on the actual issue. Most likely there is a date field explicitly filled out on the issue that overrides the automatic assignment of sprint start/end dates.

Hope this helps! 

Eldad Dayagi
Contributor
March 15, 2023

I exported the issue with all the fields and there is no such date.

I did however notice that when I right click the issue in roadmap, I see that it is linked somehow to all my future sprints.

My UI or exported fields data doesn't show any such connection.

Morevover, the issue was already completed in my last sprint.

Not sure where to go from here TBH.