Hi All,
I would like to split a Kanban's column in different status. I dont want to modify my workflow , i want only to implement a single status
Columns, statuses and the workflow go hand-in-hand. How you add a status is via the workflow, so you won't be able to add a status without changing the workflow.
I'm not sure why you don't want to change the workflow, but you are able to make a copy of it so that this change wouldn't affect other projects if they use the same workflow.
Hi @Warren
I dont want to change wfs because we dont want to have ad ex "to do" "Progress of to do" "done Of to do" "reopened of to do" . I think that is not the best option of a way to do. Also about the transition from a status to another one.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I am in the same situation as Fransesco - I have created dashboards and some Power BI metrics (as Jira standard dashboarding possibilities are frankly not very good).
Changing the workflow means all metrics have to be re-configured.
If you look at e.g. Azure DevOps, you can select to split a Kanban column into "Doing + Done", and even add your own columns. Each column still reference a default status in the workflow, so it is only the visualization that changes.
Even when multiple teams use the same ADS project & workflow, they can customize their Kanban board, and no high level metrics have to be changed - that's pretty neat.