Hello Experts,
I am using JIRA Plans on cloud version. The View setting is modified as GROUP by "Sprints".
While I can see the Jira Issues group-by the Sprints, Is there a way to see the Sprint Dates in the Plan.
Thanks
Hi @Puneet Gupta
Not directly. When you group by Sprints in Advanced Roadmaps (Plans), Jira shows the issues under each sprint, but it does not display the sprint start and end dates on the timeline by default.
[JRACLOUD-92509] Show Sprint info in Plans when not using Issue Source "Board" - Create and track feature requests for Atlassian products.