Hi guys,
I have completed "sprint 5" and moved all remaining issues to a "sprint 6". Some of the issues now have both sprint values.
The problem is that the "sprint 5" value is locked and cannot be removed. The sprint is already closed.
I have tried bulk change and only the new value is removed. No matter what I do I cannot remove the value for the completed sprint.
Any ideas?
Thank you
Hi,
Please Re-open completed sprint then try bulk change.
Hi Ramesh,
At the moment I cannot reopen the old sprint as it will mess up the issues that we have already moved to the new sprint. We have deleted/created new stories for those that had the problem.
Now it makes sense that a reopened sprint will allow you to change that value.
Thank you for the answer.