Sprint Report – Can we have Estimated time instead of Story points?

koteswararao
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 27, 2019

Sprint Report – Can we have Estimated time instead of Story points?

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 27, 2019

If you change the board to use Estimates instead of Story Points, the Sprint Report will follow.

koteswararao
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 27, 2019

can you please tell me the process steps

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 28, 2019

Go to the board, click configure, go to the estimation tab, change the field selected for estimation.