On the release burndown report I see no issues were completed for some of my sprints, but when I look on the sprint burndown I can see that must of the tickets are completed. Why? How can I solve it so the release burndown will show me the real image of the release status?
I would suggest to check if you have selected the relevant release version in Release burndown if there are multiple releases . As release burndown shows how your team is progressing against the work for a release
Thank you for your answer. I checked, and I have selected the right release. I still see only part of the sprint associated with the release :(
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.