Sprint burndown chart not showing remaing effort

natalia
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 6, 2018

My sprint burndown chart does not show the red line (remaining effort) . until last sprint the line was drawn....can you help me?

1 answer

0 votes
Fazila Ashraf
Community Champion
February 13, 2018

Hi Natalia

Make sure that your board has 'time tracking' set to "Remaining Estimate and Time spent" in the Estimate tab of the board's configure section.