Hi community,
I'm trying to use plan to track stories from different sprint in the plan.
Firstly, issue hierarchy is initiative--> Epic --> story. Initiative and Epic are in the same project. But stories are in another project. I use a JQL "
issue in portfolioChildIssuesOf("PPMD-2")
" where PPMD-2 is my initiative as a filter to create a scrum board. And I create a plan based on this scrum board. In the view setting, I choose to group issues by sprint. My goal is to show sprints on the timeline. But I don't know why it's not working.
Below is the screenshot.
Hi @Yi Meng ,
It only works if you have team assigned in issues and the team is added in plan
team in plan set to:
issue source = board should be a scrum
planning style = Scrum.
Then view settings - group by sprint - check show capacity on timeline
Thanks @Dexter de Vera
It works when I change view setting to group by team and check 'show capacity in timeline'.
I think it would be nice if Atlassian can make it possible to show sprints on timeline without team assigned to stories.
Thanks for your help.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.