Sprints not closed/completed

DarkKnightess
Contributor
May 3, 2018

I have just taken up a project as Scrum Master and I am seeing that all the previous sprints have been kept open and not marked as Closed/Completed.

I am not sure what the reason is but this seems wrong to me. The velocity chart is not getting reflected since sprints are not marked as closed or completed.

Can anyone please help me in understanding what all will be the impacts or any other places where I will see impact because of this in case the Sprint is kept open. Are any of the charts/reports impacted due to this?

1 answer

1 vote
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 4, 2018

Most of the Agile reports - Burndown chart, Sprint chart, Velocity chart etc - would be impacted if a Sprint is left open. And it is definitely not a good practice.

You should probably find out why they did it and figure out the right way to address the issue they were originally facing. Whatever it is, I would close all past sprints and start over!

DarkKnightess
Contributor
May 4, 2018

Thanks Jobin.