Start a Sprint: missing the "Start" button

Eran Shmueli October 29, 2018

Hi Guys,

My sprint starts in 2 days (31.10) and I want to start it with that date.

Currenly NO running sprints.

When I access the start sprint box, I fill in the info and then no "Start" button.

I see this message: Issues SP-125, SP-111, SP-110, SP-108 and 4 others do not have a value for the 'Remaining' field. Values entered after the start of the sprint will be treated as scope change

Notice: the team creates sub-tasks under each user story, and within the sub-task we have the original estimate (can the US calculate the estimate automatically?)

How can I start the sprint?

Thanks,

Eran

1 answer

0 votes
Mirek
Community Champion
October 29, 2018

Hi @Eran Shmueli,

Please check below KB article

https://confluence.atlassian.com/jirakb/start-sprint-warning-792311695.html

If you are still not able to start the sprint after applying the resolution then try to type 0 in Estimate field for affecting issues.

https://confluence.atlassian.com/jirakb/scope-change-warning-779159195.html

Eran Shmueli October 29, 2018

Original estimate is empty on the user story level, but updated on the sub-task level.

Is there an option to calculate the field at the US level from the Sub-Task/s?