We are using 1 sprint for all projects, so each project has its own board but we all use the same sprint created in one particular project.
The problem is when we close the sprint from one specific board, it only moves the tickets from the current board (even-though in the message the total includes the other boards :s ) to the next sprint.
I guess this is a bug. I tried creating one board with all tickets and same issue, it only takes the tickets from the project that is linked to the board.
Does anyone uses 1 sprint for several projects? do you have this issue?
We have shared sprints between projects. To fix the issue you are seeing I updated the query for that board to include all the projects that shared the sprint. When I close the sprint it should move the issues accordingly. Give it a go and see if it helps.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.