Hello All,
It has been evident that some of Epic start/end date is getting unassigned and showing blank. However in the same project most of Epic has correct start/end date.
We are using Bigpicture as a plugin. Does it has impact on start/end on Epic level...
In Jira, open one of the Epics that has blank start/end dates, and then inspect the information in the "History" and/or "Activity" tabs. Look for changes to those date fields, and see if you can identify who or what is changing them. There are lots of possible things that could cause it:
Identifying "who" is changing those fields is a good first start to tracking it down.
This is being updated by BigPicture due to syn start/end date between JIRA/Big Picture.
Shall I need to reset tasks scheduling from "auto" to manual in Bigpicture. What action is required to do so.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I'm not familiar at all with BigPicture, sorry.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.