I want to start multiple sprint active at the same time, and I have set up parallel sprint like this link, but its not working.
How can i do now ?
I understand now, thanks for your quick respond
No, it's not necessary. So unfortunately, at this point in time, the Next-Gen projects are unable to handle parallel sprints, only the classic ones can.
I believe this has answered your question, even if it's not the answer you were hoping for :-)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for your feedback!
Yah, as you mention, i am using Next-Gen project (Scrum) ?
Do you still want me to send you a picture ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Are you in a classic project or a next-gen project? At the top of the link that you added, it specifically says that parallel sprints are only for classic projects.
If you're using a classic project, what are you seeing (or not seeing)? What is happening or not happening? You say "it's not working", but we need more details of what "it" is. Possibly give some screenshots of what you're seeing