Hi Atlassian Community,

 

We are confused about something in our Jira Software Cloud instance. Every Monday, old issues that are already closed are being moved automatically to the next sprint. It shows that our project manager is the one who performed the actions in the history, but she is in a meeting each time it occurs Monday morning and not working in Jira. Any suggestions would be helpful. 

Is there a feature in Jira that would auto shift these?

Would the stories not having a resolution set cause the issue?

1 answer

0 votes
Randy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 9, 2020

Looks like you have automation in place that may be doing that.  If you have scriptrunner enabled, checkout the scheduled tasks list.

Andy Creech
Contributor
March 9, 2020

Thanks Randy, we have looked at Scriptrunner, but have not started a Trial yet. Also we have trialed Automation for Jira, but did not implement any rules around sprint planning. 