I am using advanced roadmaps to try to help my leadership understand what is happening. However, the Epics are not rolling up the dates of its children. My preference would be to have it infer dates from sprints, but even when the user stories have dates assigned it still does not roll up.
Hello @Eirik Aune
Take a look at this document and let us know if it answers your question.
https://support.atlassian.com/jira-software-cloud/docs/how-advanced-roadmaps-rolls-up-dates/
Also make sure you have the Roll-up Dates option selected in your View Settings.
Trudy, I had found the link but I had not found the magic checkbox! That got it. Thank you!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.