Stories do not roll up due dates to Epic in Advanced roadmaps

Eirik Aune
Contributor
April 26, 2023

I am using advanced roadmaps to try to help my leadership understand what is happening.  However, the Epics are not rolling up the dates of its children.  My preference would be to have it infer dates from sprints, but even when the user stories have dates assigned it still does not roll up.

 

image.pngimage.png

1 answer

1 accepted

0 votes
Answer accepted
Trudy Claspill
Community Champion
April 27, 2023

Hello @Eirik Aune 

Take a look at this document and let us know if it answers your question.

https://support.atlassian.com/jira-software-cloud/docs/how-advanced-roadmaps-rolls-up-dates/

Also make sure you have the Roll-up Dates option selected in your View Settings.

Screen Shot 2023-04-27 at 3.54.30 PM.png

Eirik Aune
Contributor
May 1, 2023

Trudy, I had found the link but I had not found the magic checkbox!  That got it.  Thank you!

Like Trudy Claspill likes this