We have a project in which each story requires work on multiple components and environments . Each task is done by a separate team member and is needed to complete a story .
E.g Story S1 needs -
XML to be created
XML to be loaded
ETL to be created
ETL to be loaded
Config to be updated
Each of these tasks has to be done on Dev , QA & production for it to get completed. Majority of the time , all these cannot be completed in the same sprint for the story to be done .
Need thoughts on how stories should be broken up so that its completed in a sprint and how should environment specific tasks be managed ?
Thanks
Don't comingle stories with change controls, use different issue types. For example:
S1 - Status: Costomer Signed Off, Issue Type 1 (Many tasks to get to this status)
CC1 - Promote S1 to Pre-Producrion Alpha - Issue Type 2 (Triggered when main S1 issue Status = Customer Signed Off
Compartmentalize stories based on the services layer to optimize well built stories flowing through environment progressions, this will reduce the number of times you have to touch the code for the story, ultimately saving costs.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.