Turns out the Estimation feature said it was "on" in the interface but was "off" in the backend. Support team fixed it.
Thank you.
Hi @Phil - You might also need to add the Story point estimate field to the issue type you want to add estimates to. Here's how:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
By default the Time Tracking section won't display for an issue if there is no original estimate. Go to the detailed issue view of a given issue, click the edit look for Original Estimate and if found add in an estimate, save it and see if Time Tracking now displays. If OE is not in the Edit view you need to add the field to the screen, details of which will depend on if you are on server or cloud.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.