liya May 27, 2025

I can not see the story point summary from subtasks. 

I need see each developer's effort estimation. Could anyone help with this?

image.pngubtasks.

3 answers

0 votes
Karan Sachdev
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
May 27, 2025

Hey @liya

Welcome to Atlassian Community!

Story points for Subtasks are not considered by default since these are not considered independent work items. We have a suggestion ticket related to this: https://jira.atlassian.com/browse/JRACLOUD-90772

As @Piyush Annadate _ACE Pune_ has suggested, an automation rule would be the workaround here. Unfortunately, it doesn't give the complete picture when you filter for a developer who has only subtasks assigned to them. This would require manual effort.

Thanks!

0 votes
liya May 27, 2025

 Thanks for your reply.

As you see in the screenshot, numbers 1 and 0.6 are all story points for subtasks. 

The main user story might be split into multiple subtasks and assigned to different developers.

When I am looking for effort estimation for a particular developer, the story points from subtasks are not calculated. I will be confused by the numbers.

 

And below is the setting for my board configuration. Let me know if you need any more details.

image.png

 

Piyush Annadate _ACE Pune_
Community Champion
May 27, 2025

Hi, The story points are not calculated as sum from subtask to parent; you may need to have an automation to perform that. 

Trigger, Story points field update,
Condition: Type is story points
Action: Calculate the parent sub task story points and update the parent. 

liya May 27, 2025

Hi,

The solution proposed is only to make sure the parent task will have a summarized story point.

But when I only filter out a particular developer, he/she might only have subtasks, how to see the summary for the subtasks' story points?

0 votes
Piyush Annadate _ACE Pune_
Community Champion
May 27, 2025

Hello @liya ,
Welcome to the Atlassian Community !
Can you confirm if your subtask has STORY POINTS populated?
I would suggest, to have story points at STORY LEVEL only, which is better process.

Anyhow, check your board config for estimation is having STORY POINTS or other calculation field?Screenshot 2025-05-27 at 3.01.54 PM.png