Hello the story points are missing after migration from a Team based Project to a company based project in JIRA.
Unfortunately I am unable re-migrate because the original project does not have those stories any more.
Any idea what happened!
In Team Managed projects the story point value is in the Story Point Estimate field.
In a Company Managed project the story point value is in the Story Points field.
Since these are different fields, the information does not automatically migrate.
The loss of the Story Point Estimate data is called out in the documentation about migrating issues from a Team Managed project to a Company Managed project.