I know there are many issues about this already and I read through SO MANY of them, and it still won't work.
BUT, whatever I try, I cannot get a csv file with Epics, Tasks, Stories, Bugs, and Subtasks to import the Subtasks.
I am an Admin and we are on the Standard plan.
Questions:
Thank you so much - what a faff these Subtasks are!
To import parent/child relation for sub-taks you need to have to extra column in your csv.
See, this KB artivcle, https://support.atlassian.com/jira/kb/keep-issue-parent-child-mapping-during-csv-import-to-jira-cloud/
extra columns are added, in the KB they are "issue id" and "parent"
Both of these are already in the csv and have data in it. They are also mapped to the fields in the new Space. It still won't work.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Then your mapping might be incorrect.
Also please show a part of your CSV.
Also issue id and parent should not contain issue key codes.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Saskia van _t Hoff ,
first of all: It's not you. Subtasks import is a real bitch.
Your questions:
1. Definitely not. Your reordering approach was fine. You need to respect the work item hierarchy, of course. What I take you did.
2. No, 'Parent' is not enough to link Subtask and any work item within the same import. To transport this relation you need 'Issue ID' and 'Parent'. These two provide a .csv internal relation between work items and their subtasks. You could create this relations yourself by giving the very first item in your .csv e.g. ID '1' and have all its subtasks reference '1' as parent and so on. In your case this information ought to be intact already, since it came with the export you did. But however: This might be worth checking.
3. Yes, you can create the subtasks via a second/ later import.
4. This I can't answer. But i doubt that loosing the status is the only thing here. When there is only an emtpy space everything a work item needs is missing: screens, workflows... So my best guess here is: No, this will not work.
Some generic advise for your usecase:
Always do very little portions first on import, see what is the outcome. Create just one level 0 work item and its subtask. Create one branch of work item hierachy. And only if all this runs fine do the whole bunch.
And just to make sure: The work items you want subtasks attached to do end up on level 0?
Good luck and cheerio,
Sascha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Wait a second... are these just 'subtasks' or do they have a specific name? In your export: What do the subtasks have in column 'Type'? When they have a specific name they might not be recognized as subtasks during import at all.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Saskia,
You can create the parent and the child at the same time. Or you can create the child and reference the key of the parent when you import the child.
In my example below I have using Epic and Story, but Task and Sub-task would be the same process.
The last example is if you are just creating new Sub-task and linking it to an existing parent.