My subtasks are all marked with status of "Done" and the parent ticket is status "Done" and parent ticket resolution is either "Resolved" or "Fixed" but the subtasks persist as "Unresolved". SO, SO, SO many subtasks with this issue. How do I flip the resolution from "Unresolved" to "Resolved"??
It sounds like the workflow for sub-tasks don't go through a transition that allows or automatically sets the resolution field when going to Done. you need to change that
A sub-task's status and/or resolution is independent of it's parent status and/or resolution.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Chris Dunne [GetJirified.com] @Joe Pitt @Andrea Carl Thank you all for the responses and solutions.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
As Joe and Andrea said, it sounds like you have a workflow issue. Once you fix the workflow you'll also probably need to do a bulk update to correct the subtasks that are Done but don't have a resolution.
You could use the bulk edit facility to do that. You'll just need a JQL query to give you a list of all the relevant subtasks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.