I was looking at the big picture, it shows that there are few subtasks whose remaining estimate is 0. However, the time spent is zero. i believe it should throw the value of original estimate as no time was spent on the work. I even tried to play with the settings and tried to find bulk edit the time remaining in work log but that option is not available in the bulk edit for me. Thank you in advance!
Hi @Rishav Raj
First of all, please be informed that both Original and Remaining Estimate values are stored in Jira's Time Tracking field.
In your case, I would advise you to verify if the Remaining Estimate values are correct in the Jira issues. If so, please clear the plugin cache and fix the integrity checker errors in the Technical Configuration/Advanced section.
Otherwise, please update your Jira issues accordingly so that the values are displayed in your Gantt chart.
I hope that this helps.
Best regards,
Mateussz Sołowianiuk
SoftwarePlant Support
Thank you clearing cache worked like a charm!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Great news, @Rishav Raj I'm glad that you are now able to benefit from all the functionalities of the plugin.
Best regards,
Mateusz Sołowianiuk
SoftwarePlant Support
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.