×By default sub-tasks have a hierarchy level of -1, which doesn't show in the Timeline view, even with Advanced Roadmaps.
How can the hierarchy level be changed to show sub-tasks ?
Hi @YJ Rodrigues ,
Hope this knowledge article helps. This will show how to display sub-task in advanced roadmaps.
-Ben
Thanks Benjamin.
Unfortunately that article explains how to convert sub-tasks into tasks, which is not what I wanted, as that would destroy my hierarchy of tasks.
In Jira server, there used to be a way to create an adhoc hierarchical view of issues (regardless of the type) using the Structures
Is there anyway to do something similar in Jira Cloud ?..