Hello,
Our project included Bugs, Stories and Support-Task. The value of Story Point doesn’t appear from Support-Task issues.
Can someone explain us? Is a problem of Support-Task configuration or Support-tasks do not admit this value (Estimate as Story Points)?
Regards,
Jorge.
Hello,
It is somewhere in the configuration. You should add the Story Point field to the view and edit screens for the Support-Task issue type. If you need the Story Point field in the create screen, then you can also add the Story Point field to the create screen.
Thanks for your answer @Alexey Matveev,
Yes, probably our problem is in the configuration because if we are in Active Sprint tab and we select any SupportTask issue, in his Edit tab (Configure Fields-->Show Fields: All-Custom) we don't view StoryPoints field thus we can't add it.
Do you know what is the way for add the Story Point field to all Support-Task issue?
Regards and thank you again.
Jorge.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You need to add the Story Point field to the Edit screen for the Support-Task issue type. You can find more info here:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.