Dear Community!
I have an important question, as cannot find answers on the internet (or not straight enough). We will use the time tracking solution provided by Atlassian in JIRA, therefore it makes more sense for us to switch estimating stories and tasks from Story Points to Time.
Although, I cannot find the information about the JIRA report's behavior - are those gonna be automatically adjusted to the new option, or shall we take additional action adjusting them manually?
The same goes for Sprint Insights available on our boards.
I would be grateful for your quick support on this topic.
Cheers,
Adrian Sz.
Hi @Adrian Szubert,
The Jira boards and reports will not change automatically. You will have to manually reconfigure them.
For tracking / reporting you could try also our Great Gadgets app. It offers many gadgets (including sprint burndown chart, release burdnown chart or team velocity) that works with both story points and time estimates.
Have a look over this blog article to make an idea: Tracking an agile project that uses time estimates with Great Gadgets for Jira
I hope this helps.
Danut Manda
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.