Target Start/Target End dates in a Structure View vs. Plan View

Jessica Dosio January 26, 2022

Hello! I would like to understand why the Target Start/Target End dates in a Structure View are showing as 1 day prior to the Target Start/Target End dates for the same issue in Plan View? Is this a known issue?

1 answer

1 accepted

1 vote
Answer accepted
David Niro
Atlassian Partner
January 27, 2022

Hello @Jessica Dosio ,

David from ALM Works here.

What version of Jira are you currently using?  There was a bug identified where Target Start and Target End fields store incorrect values in CEST within jira create rest calls JPOSERVER-2358.

It was resolved in Fix Version/s:  8.20.2, 8.21.0, so an update may be required.

If you are using one of the versions that the issue should be resolved in, could you please send a note to our support team via email support@almworks.com or customer portal support.almworks.com.

Please let me know if this helps.  I look forward to your feedback!

Best Regards,
David Niro

Jessica Dosio January 27, 2022

Thank you for the quick reply, David. Based on the below information, it would appear we are using a very outdated version of Jira which is why I am seeing this issues, correct? 

License Information for Jira

Jira v8.6.1

Copyright © 2002 - 2020 Atlassian Corporation Pty Ltd.

David Niro
Atlassian Partner
January 27, 2022

Hi @Jessica Dosio ,

You are very welcome!   

This does appear to be the case.  If for some reason the issue persists after upgrade, please reach out to our support team and we will be happy to review in more detail!

Best,
David