Tasks are showing incomplete in the sprint.

Samiullah Khan
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 4, 2018

I am facing a problem , I have created a sprint and there were 5 tasks in it ,Among those 3 was tasks and 2 were bugs . What I did. # Four tasks completed #1 task rejected but in the sprint status it is showing only 1 task is completed. # When I create new sprint the completed done tasks are moving in that sprint too. Here is my flow screenshort and sprint details as wellWorkflow.pngImage.pngImage 2.png

1 answer

2 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 4, 2018

Your screenshot of the board shows that you have only "done" one issue.  Jira uses the right hand column to define what is done.  

I would consider merging your "done" and "rejected" columns together into one column, or just moving your "done" into last place.